Overall feasibility
Proceed to site verification and preliminary professional review.
The concept is viable within the stated brief. Confirm land approval, utility connection distance and clear delivery access before design freeze.
Assessment PM-24001 · Guided demo
Kwun Tong120 sq.ft.HK$400,000 budgetTarget: 6 months
Overall feasibility
Proceed to site verification and preliminary professional review.
The concept is viable within the stated brief. Confirm land approval, utility connection distance and clear delivery access before design freeze.
Decision profile
Evidence-led findings
4 demo findings
No land allocation, tenancy or written site-authority document has been supplied.
Next: Confirm the land controller and obtain written permission before detailed design.
The brief confirms that power is nearby, but gives no route or measured distance.
Next: Survey the connection point and update the M&E allowance.
Vehicle access is indicated, but the narrowest turning and lifting clearances are not recorded.
Next: Complete a delivery-route survey before locking module dimensions.
The 120 sq.ft. target and twenty-person peak brief fit the demo configuration assumptions.
Next: Proceed to a measured layout and operator review.